Friendship Village of Dublin is in the midst of a multi-year expansion project that will revolutionize retirement living in central Ohio. The campus-wide expansion at Friendship Village of Dublin will redefine comfort, convenience and choice in senior living. The crown jewel of the expansion project is The Flats at River Point, a new independent living …
We’ve hit some major milestones this week including the final touches on the Pavilion and wood stairs in one of the Flats Towers! It’s been great to see the progress we made over the fall and we’re excited to continue the hard work! Check out what the next two weeks will look like for us: …
While the framing is continuing for the Flats, the Riverstone apartments are getting foundation poured. The finishing touches are being put on the pavilion today and it will soon be available for everyone to enjoy! Check out the other updates: Garages Clean up landscaping Continue irrigation along street Utility Pump House/Entry Feature Gutters and …
Our 16-unit Flats building is being framed with the other 3 buildings to follow. See construction update below: Sitework & Utilities Perform permanent sanitary reroute now that city has signed re-design Garages Clean up landscaping Start irrigation, subcontract Award letter sign for Oakland Irrigation RCC and Andy Howland to finalize trees with Darby …
Our residents love taking some time to enjoy the weather, which is why we’re making it a priority to work on our new pavilion this month. When completed, this will be a great area for everyone to enjoy! See what else we have planned: Sitework & Utilities Transfer Water Tie-ins Tuesday and Wednesday night …
The walls are coming down and Riverside is one step closer to being completed. We’ve also continued making progress on the Stone Wall installation for the Utility Pump House. Check out what else is going on: Sitework & Utilities Complete Boulder outcroppings along sidewalk to Villas Garages Re-grade and compact parking lot …
Friendship Village of Dublin in the news! http://www.thisweeknews.com/content/stories/dublin/news/2016/07/05/friendship-village-of-dublin-builders-make-headway-on-61-million-project.html
The summer heat hasn’t slowed down our progress. While many of our friends are vacationing, we are continuing to make big steps in our renovations. Here’s what you’ll see for us in the month of July: Sitework & Utilities Complete Boulder outcroppings wall Garages Demolish the old garages, July 5th Flats Building …
Our biggest news this week is that the foundation at the flats has been poured, but the work doesn’t stop there. Here’s what we have planned for the next two weeks: Sitework & Utilities Complete Boulder outcroppings wall Garages: Demolish the old garages, July 5th Utility Pump House/Entry Feature Finish valve installation …
It was all hands on deck today as our residents started to move items into their new garages. The excitement doesn’t stop there; there’s been progress made on both the Flats and Riverstone Apartments! Check out our plans for the next two weeks: The Flats Building 6772: Continue Foundation CMU Walls, Elevator Pit waterproofing and …